Contract signed: December 2016
Topside campaign
Offshore start: June 23, 2019
Offshore end: July 27, 2019
Jacket campaign
Offshore start: July 11, 2020
Offshore end: July 16, 2020
Removing the Jotun B platform from the North Sea over two campaigns with Thialf and Sleipnir
Lifting the 8,100 metric ton jacket
Removing the 8,100 metric ton jacket
On the way to deliver the jacket for recycling
On the way to deliver the jacket for recycling
Offloading the jacket onto the quayside at the AF Miljøbase decommissioning site in Vats, Norway
Heerema’s scope was to provide all Engineering, Preparation, Removal and Disposal (EPRD) activities for the removal of the Jotun B platform in the North Sea. The offshore removal was split over two campaigns. The first removal was the 2019 Thialf campaign to remove the 7,360 metric ton Jotun B topside. Thereafter, in 2020, Sleipnir removed the 8,100 metric ton jacket – a record breaking single jacket lift at the time.
The Jotun Field is located in block 25/7 and 25/8 in the Norwegian sector of the North Sea and is located approximately 180 km west of Haugesund, Norway. The Jotun B wellhead platform was installed by Heerema in 1998, demonstrating the circularity of Heerema’s decommissioning operations.
Thialf arrived on location on June 23, and started the campaign with the removal of twenty-two conductors that were cut below the seabed by abrasive water jet. These conductors were lifted and cut into four pieces, before being laid on Thialf’s deck. After which, the Jotun B integrated deck topside was removed in a single lift within five hours. Thialf sailed to the AF Miljøbase decommissioning site in Vats, Norway with the topside suspended from its cranes.
For the jacket removal, Sleipnir arrived at the Jotun Field on July 11, and completed the removal one day ahead of schedule on July 16. During the jacket removal, skirt piles with diameters 108” (2.7m) and 80mm wall thickness were cut subsea, the largest ever done in this way. Additionally, Heerema modified an existing 40m long spreaderbar within 2mm length tolerance. The jacket was sailed to Vats suspended in Sleipnir’s cranes, and will now be recycled up to 98%.
Contract signed: December 2016
Topside campaign
Offshore start: June 23, 2019
Offshore end: July 27, 2019
Jacket campaign
Offshore start: July 11, 2020
Offshore end: July 16, 2020
Topside campaign
Thialf
Kolga
Jacket campaign
Sleipnir
Topside campaign
DES: 915 metric ton
Conductors: 2,705 metric ton
Skid base: 220 metric ton
Topside: 7,360 metric ton
Conductor Support Frame (CSF)
Jacket campaign
8,100 metric ton
40m long spreaderbar
Want to discuss how our solutions can help your decommissioning project? Get in touch with one of our experts!
Join the Heerema team!