Procurement & construction
Jacket construction for the Hejre field
Heerema Fabrication
Dong Hejre Jacket
HFG completed the construction of the launch jacket for the Hejre field in 2014.
At a glance
- Procurement and construction of 8,500 ton launch jacket and pre-drilling wellhead deck
- Construction completed in 2014
- After construction, the jacket was successfully installed in the Danish sector of the North Sea.
The Heerema promise
Technip & Heerema:
Procurement and Construction
The contract for the procurement and construction of the launch jacket and pre-drilling wellhead deck for the Hejre project was awarded in 2012. Fabrication started at the Vlissingen yard in January 2013. In May 2014 the jacket set sail to its final offshore destination in the Danish sector of the north sea.
The project comprises the fabrication of a launch jacket of 8,500 tonnes for the Hejre field. For the installation of the 8-leg launch jacket two buoyancy tanks were constructed, 400 tonnes each. They were installed on both sides, to keep the jacket floating after launch. The jacket was successfully installed in the Danish sector of the North Sea during 2014.
Key information
Contract type
Location and Milestones
Location
Danish North Sea
Project Completion
2014
Structure and Characteristics
Jacket
Size (LxWxH): 60 x 35 x 85 m
Weight: 8,500 tons
Pre-drilling wellhead deck
Size (LxWxH): 40 x 12 x 10 m
Weight: 900 tons